Install seven modular buildings and compliant in sixteen days.

THE CHALLENGE


MACS were called in to restore the Broome’s Classroom before the students came back from holidays 2020, after an escapee prisoner set alight to the school destroying Broome local primary school. In a quick response MACS restored/replaced the classrooms destroyed by fire in time for the students to return for 2020. Installing modular buildings on an active demolition site that included significant friable asbestos removal The full extent of the connectivity of existing services was unknown until the second week, so several different options needed to be explored and ready to execute.

Capabilities

Planning

Design

Construction

THE RESULTS